2018/41 Spanish Supreme Court now aligned with ECJ’s case law: Limitation to pre-transfer liabilities for new contractor under CBA-led transfers that triggers a non-asset based transfer are not valid (SP)
Following the ECJ’s decision in Somoza Hermo – v – Ilunion Seguridad, C-60/17 (Somoza Hermo) of 11 July 2018, all eyes were on the Spanish Supreme Court. Since 2016, the Court has ruled a number of times that limitations to the liability of the new contractor established in a collective bargaining agreement (‘CBA’) in the context of a CBA-led transfer were valid (see e.g. EELC 2018/21). Somoza Hermo established that a CBA-led transfer that entails a non-asset-based transfer is a transfer within the meaning of the Acquired Rights Directive. Now the Supreme Court (in a decision dated 27 September 2018 taken with one dissenting opinion) is clear that its doctrine must be reviewed and has therefore held that limitations on pre-transfer liability for a new contractor under a CBA-led transfer that trigger a non-asset-based transfer, are not valid.
Tribunal Supremo de España (Spanish Supreme Court), 2018-09-27